Assembly Architecture and Assembly Sequence in General Machinery

Assembly Architecture and Assembly Sequence in General Machinery

1. Definition of Assembly Architecture and Sequence

Assembly Architecture and Sequence is the discipline that defines how a machine is divided into assembly units and how those units are combined according to specific references and sequences to form the complete machine.

Assembly Architecture determines:

  • How the machine should be divided into hierarchical levels

  • Which parts should be grouped into a single subassembly

  • Where the physical and functional boundaries of each module should be located

  • At which stage each module should be tested independently

  • Which areas can be outsourced or assembled in parallel

  • Where the machine should be separated for transportation and field installation

Assembly Sequence determines:

  • Which parts should be installed first

  • Which parts must be assembled before others

  • When alignment, adjustment, and inspection should be performed

  • At which stage temporary fastening and final fastening should be applied

  • At which stage wiring and piping should be performed

  • What must be verified before covers are closed

The essence of this discipline is therefore:

To design the machine’s assembly structure and assembly flow so that the same quality and functionality can be reproduced consistently.

2. Purpose of Assembly Architecture

Assembly Architecture is not simply the task of dividing a product into several assemblies.

It should achieve the following objectives simultaneously.

2.1 Simplification of Assembly Work

  • Divide complex assembly work into manageable units.

  • Reduce the scope that an operator must handle at one time.

  • Clarify assembly references and inspection criteria.

2.2 Enabling Parallel Work

  • Allow machine modules to be assembled simultaneously.

  • Reduce total production lead time.

  • Separate outsourced assembly from in-house assembly.

2.3 Quality Assurance at Module Level

  • Verify function before final machine assembly.

  • Limit defects to the module in which they occur.

  • Avoid disassembling the entire machine during rework.

2.4 Support for Product Variants

  • Allow modules to be replaced or added according to product specifications and options.

  • Reuse the same basic structure across multiple machine models.

2.5 Support for Transportation and Installation

  • Divide the machine into transportable sizes and weights.

  • Allow reassembly at the customer site while maintaining positional repeatability.

3. Purpose of Assembly Sequence

The assembly sequence is not intended only to reduce working time.

It directly affects:

  • Assembly accuracy

  • Risk of part damage

  • Tool accessibility

  • Inspectability

  • Work safety

  • Rework capability

  • Production time

  • Dependence on operator skill

An incorrect assembly sequence may cause:

  • Installed parts to be removed again

  • Internal bolts to become inaccessible

  • Wiring or piping routes to become blocked

  • Alignment reference surfaces to become hidden

  • Heavy parts to be installed in unstable conditions

  • Covers to be closed before inspection

  • Multiple modules to be removed to replace one failed part

4. Hierarchy of Assembly Architecture

The assembly structure of general machinery is typically organized into the following levels:

  1. Part

  2. Component Assembly

  3. Subassembly

  4. Functional Module

  5. Machine Module

  6. Complete Machine

  7. Production Cell or Line

4.1 Part

A single manufactured or purchased item.

Examples:

  • Plate

  • Shaft

  • Bracket

  • Bearing

  • Sensor

  • Valve

4.2 Component Assembly

A basic assembly consisting of a small number of parts.

Examples:

  • Shaft and bearing assembly

  • Motor and reducer assembly

  • Cylinder and bracket assembly

4.3 Subassembly

An independent lower-level assembly installed into a higher-level module.

Examples:

  • Ball-screw drive assembly

  • Clamp assembly

  • Valve-manifold assembly

  • Operator-panel assembly

4.4 Functional Module

An assembly unit that performs one clearly defined function.

Examples:

  • Feeding module

  • Alignment module

  • Clamping module

  • Inspection module

  • Discharge module

4.5 Machine Module

A large module that forms a major section of the machine.

Examples:

  • Base module

  • Processing module

  • Control-panel module

  • Safety-guard module

5. Criteria for Dividing Assembly Units

Assembly units should not be divided based only on function.

The following criteria should be reviewed together.

Functional Criteria

  • Does the unit perform an independent function?

  • Does it have clearly defined inputs and outputs?

  • Can its function be tested independently?

Physical Criteria

  • Does it have an independent frame or mounting surface?

  • Does it have separable fastening points?

  • Is its size and weight manageable?

Interface Criteria

  • Is the mechanical interface simple?

  • Can the electrical interface be separated using connectors?

  • Can pneumatic and hydraulic connections be disconnected?

Production Criteria

  • Can it be assembled in a separate work area?

  • Can it be outsourced?

  • Does parallel assembly reduce lead time?

Service Criteria

  • Can the module be replaced as a unit in the event of failure?

  • Can it be inspected independently in the field?

6. Relationship Between Assembly Architecture and Product Architecture

The functional structure of the product should correspond to the assembly structure wherever possible.

Example:

Product Function

Product Module

Assembly Module

Product Feeding

Feeding Module

Feeding Mechanism Assembly

Product Alignment

Alignment Module

Guide and Sensor Assembly

Product Clamping

Clamp Module

Clamp and Cylinder Assembly

Processing

Processing Module

Spindle and Feed-Axis Assembly

Inspection

Inspection Module

Camera and Lighting Assembly

Discharge

Discharge Module

Conveyor and Discharge Mechanism Assembly

When the functional structure and assembly structure correspond, the following become easier:

  • Design changes

  • Option additions

  • Software modularization

  • Functional testing

  • Service

  • Defect-cause analysis

7. Definition of Module Boundaries

Each assembly module requires clearly defined boundaries.

7.1 Mechanical Boundary

  • Mounting surface

  • Datum surface

  • Fastening bolts

  • Locating pins

  • Load-transmission surface

7.2 Electrical Boundary

  • Power connector

  • Sensor connector

  • Motor cable

  • Network connection

  • Ground connection

7.3 Fluid Boundary

  • Pneumatic supply

  • Exhaust

  • Hydraulic supply

  • Return

  • Cooling-fluid connection

7.4 Functional Boundary

  • Start condition

  • Operating command

  • Completion condition

  • Abnormal state

  • Recovery condition

If module boundaries are unclear, responsibility for assembly and testing also becomes unclear.

8. Reference Module and Reference Component

The module or component that serves as the reference for the complete assembly should be defined first.

Typical reference components include:

  • Machine base

  • Main frame

  • Precision table

  • Reference plate

  • Main shaft

  • Reference rail

The reference module should satisfy the following conditions:

  • It has sufficient rigidity.

  • Its deformation is small.

  • It can be measured.

  • Multiple modules can refer to it.

  • It can be installed early in the assembly process.

9. Assembly Datum System

Assembly datums should be connected hierarchically.

Example:

Machine Installation Reference
→ Base Datum Surface
→ Module Mounting Datum
→ Subassembly Datum
→ Part Datum

If the datums at each stage are defined independently, tolerance accumulation and positional mismatch may increase.

Characteristics of a Good Datum System

  • Upper-level and lower-level datums are connected.

  • Measurement methods are defined.

  • Datum surfaces are protected during assembly.

  • Datums remain verifiable after assembly.

  • The same references can be used during reassembly.

10. Basic Principles for Determining Assembly Sequence

The assembly sequence should be based on the following principles.

Reference First

Install reference parts and datum surfaces first.

Internal Components First

Install internal parts before external covers hide them.

Heavy Components First

Install heavy parts during an early stage when the structure is stable.

Protect Precision Components

Install precision components after rough structural work is completed.

Temporary Fastening Before Adjustment

Temporarily fasten parts requiring alignment or adjustment, then measure and apply final fastening.

Maintain Inspectability

Do not cover measurement surfaces or internal structures before inspection is completed.

Preserve Wiring and Piping Routes

Ensure cable and tube routes are not blocked before installation.

11. Precedence Relationship

Assembly operations have precedence relationships.

Examples:

  • Install the shaft after the bearing has been installed in the housing.

  • Install the moving table after the linear guides have been installed.

  • Close the panel cover after internal wiring is completed.

  • Adjust the sensor after the sensor bracket is installed.

  • Align precision axes after frame leveling.

Precedence relationships can be classified as follows.

Physical Precedence

The next part cannot be installed until the previous part is installed.

Accessibility Precedence

A later-installed part blocks the workspace required for an earlier operation.

Quality Precedence

Measurement and inspection must be completed before proceeding.

Safety Precedence

The structure must be safely supported or fixed before the next operation begins.

12. Assembly Precedence Diagram

The relationships among assembly operations can be visualized using an Assembly Precedence Diagram.

Example:

Base Assembly
→ Frame Alignment
→ Linear Guide Installation
→ Drive Assembly Installation
→ Moving Table Installation
→ Sensor Installation
→ Wiring and Piping
→ Cover Installation
→ Final Inspection

Where parallel work is possible, the process can be divided into:

  • Main-frame assembly

  • Electrical-panel assembly

  • Pneumatic-manifold assembly

  • Operator-panel assembly

  • Safety-guard assembly

These modules are then combined during final integration.

13. Serial Assembly and Parallel Assembly

Serial Assembly

One operation must be completed before the next operation begins.

Advantages

  • Simple workflow

  • Easy management

  • Clear responsibility

Disadvantages

  • Total assembly duration may be long.

  • Delay in one process affects the entire schedule.

Parallel Assembly

Multiple modules are assembled simultaneously.

Advantages

  • Reduces lead time

  • Allows specialized work teams

  • Supports outsourced assembly

Disadvantages

  • Module-interface errors may be discovered only during final integration.

  • Design changes must be communicated to all teams simultaneously.

  • Module-specific quality criteria are required.

14. Module Assembly and Final Integration

Where possible, modules should be completed and tested before installation into the complete machine.

Items to Complete at Module Level

  • Mechanical assembly

  • Fastening

  • Lubrication

  • Basic wiring

  • Basic piping

  • Sensor installation

  • Functional check

  • Dimensional inspection

Items to Perform during Final Integration

  • Module positioning

  • Inter-module fastening

  • Cable connection

  • Pneumatic and hydraulic connection

  • Network connection

  • Overall alignment

  • Integrated functional test

15. Temporary Assembly and Final Assembly

In precision machinery, not all components are tightened to final torque from the beginning.

Temporary Assembly

Purposes:

  • Position verification

  • Interference verification

  • Alignment

  • Tolerance adjustment

  • Wiring-route verification

Final Assembly

Final assembly should be performed after confirming:

  • Position

  • Parallelism

  • Perpendicularity

  • Concentricity

  • Travel resistance

  • Interference

  • Adjustment values

After final tightening, the assembly should be measured again to verify any change caused by fastening.

16. Assembly Sequence and Tolerance Stack-Up

The assembly sequence can affect tolerance accumulation.

For example, if several parts are connected sequentially without a common datum, the position error of the final part may become large.

Undesirable Method

Part A → Part B → Part C → Part D

If each part is referenced from the previous part, error continues to accumulate.

Preferred Method

Where possible, connect multiple parts directly to one common datum.

Common Datum Surface → A, B, C, D

The datum-transfer path should be reviewed together with the assembly sequence.

17. Placement of Alignment Operations

Alignment is not a single task performed only after assembly is complete.

Alignment may be required at the following stages:

  • Frame alignment

  • Guide alignment

  • Shaft alignment

  • Motor and coupling alignment

  • Tooling alignment

  • Sensor alignment

  • Module-to-module alignment

Each alignment operation should define:

  • Reference

  • Measuring instrument

  • Measurement location

  • Allowable tolerance

  • Adjustment method

  • Final locking method

18. Timing of Intermediate Inspection

Items that cannot be checked after final assembly should be inspected during assembly.

Items Requiring Intermediate Inspection

  • Internal fasteners

  • Bearing preload

  • Seals and gaskets

  • Internal wiring

  • Internal piping

  • Datum-surface cleanliness

  • Welds

  • Internal frame structure

A Hold Point may be established so that the next operation cannot proceed until the inspection is passed.

19. Hold Point and Witness Point

Hold Point

A point at which work cannot proceed until inspection or approval is completed.

Examples:

  • Bearing-preload confirmation

  • Linear-guide parallelism measurement

  • Internal-wiring inspection

  • Pressure-leak test

Witness Point

A point at which the inspector is notified and may attend, but work may continue under defined conditions.

Inspection points for critical assembly operations should be recorded clearly.

20. Assembly Sequence and Tool Accessibility

The following should be reviewed when planning the assembly sequence:

  • Can tools reach the bolts?

  • Is there enough room to use a torque wrench?

  • Can a press or lifting device be used?

  • Can measuring instruments be installed?

  • Is there enough reaction space for power tools?

  • Can the operator’s hands enter the workspace safely?

The presence of a fastening point in the drawing does not necessarily mean that it can be assembled in practice.

21. Assembly Sequence and Operator Posture

Operator posture affects both assembly quality and safety.

Work Conditions to Avoid

  • Overhead fastening

  • Work deep inside confined spaces

  • Manual support of heavy parts

  • Prolonged bending

  • Fastening without a clear line of sight

  • Supporting a part with one hand while fastening with the other

Improvement Methods

  • Use of rotating jigs

  • Height-adjustable workbenches

  • Use of lifting devices

  • Application of temporary supports

  • Change of assembly direction

  • Preassembly by module

22. Assembly Sequence for Heavy Components

Heavy components should be installed considering:

  • Machine center of gravity

  • Lifting points

  • Lifting route

  • Temporary supports

  • Tip-over prevention

  • Operator access

  • Fixing method after installation

Because installation of heavy components may deform the frame, level and alignment should be checked again afterward.

23. Installation Timing of Precision Components

The installation timing of precision components such as linear guides, ball screws, bearings, sensors, and optical equipment is important.

If they are installed too early, they may be exposed to:

  • Welding dust

  • Machining chips

  • Impact

  • Paint contamination

  • Stepping or contact by workers

  • Dropped tools

Rough structural assembly and machining work should be completed first, followed by cleaning and installation of precision components.

24. Assembly Sequence for Wiring and Piping

Wiring and piping are not secondary tasks performed only after mechanical assembly is complete.

Items to Confirm before Wiring and Piping

  • Cable routes

  • Tube routes

  • Range of motion

  • Cable carriers

  • Pass-through holes

  • Connector positions

  • Maintenance space

Typical Sequence

  1. Install cable trays and ducts.

  2. Install cable carriers.

  3. Install main power cables.

  4. Install sensor and signal cables.

  5. Install communication cables.

  6. Install pneumatic and hydraulic piping.

  7. Apply labels.

  8. Verify connections.

  9. Install protective covers.

25. Timing of Cover and Guard Installation

Covers and safety guards are generally installed after internal assembly, wiring, piping, and inspection are completed.

However, some safety guards may also be required during assembly work.

Items to Confirm before Cover Installation

  • Completion of internal fastening

  • Cable fixation

  • Piping-leak verification

  • Completion of lubrication

  • Removal of foreign matter

  • Sensor adjustment

  • Completion of intermediate inspection

Because internal inspection may become difficult after cover installation, inspection results should be recorded.

26. Assembly Sequence and Functional Testing

Functional testing should not be performed only after final assembly.

Testing by Stage

Part Level

  • Rotation condition

  • Sensor operation

  • Valve operation

Subassembly Level

  • Shaft rotation

  • Cylinder movement

  • Brake operation

Module Level

  • Functional operation

  • I/O verification

  • Leakage

  • Accuracy

Complete-Machine Level

  • Functional coordination

  • Sequence

  • Safety

  • Performance

Testing by stage allows the defect location to be identified more quickly.

27. Assembly Sequence Considering Rework

The assembly sequence should consider not only normal assembly but also rework.

Review Items

  • At which stage can a defective part be detected?

  • How many surrounding parts must be removed for replacement?

  • Which items must be re-inspected after reassembly?

  • Which parts cannot be reused?

  • Must locking compound or seals be reapplied?

If rework requires disassembly of the entire module, the assembly structure should be reconsidered.

28. Sequence Design for Assembly Error Prevention

The assembly sequence itself should help prevent errors.

Application Methods

  • Prevent progression to the next step when the wrong part is installed.

  • Make fastening impossible when the orientation is incorrect.

  • Prevent the cover from closing when a required part is missing.

  • Allow the next operation only after barcode verification.

  • Require fastening-completion confirmation before progression.

  • Include automatic sensor testing in the assembly process.

29. Product Options and Assembly Sequence

Where product options exist, standard assembly and optional assembly should be distinguished.

Option-Management Items

  • Applicable model

  • Additional parts

  • Removed parts

  • Wiring changes

  • Piping changes

  • Software functions

  • Inspection conditions

  • Changes in work sequence

The later an option is introduced, the more likely it is that completed areas must be disassembled.

Options should therefore be identified as early as possible in the assembly process.

30. Assembly Sequence and BOM

The BOM should reflect the assembly structure rather than being only a list of parts.

Example BOM Hierarchy

  • Complete Machine

    • Base Module

    • Feeding Module

    • Processing Module

    • Control Panel

    • Safety Guard

    • Pneumatic Module

When the BOM hierarchy corresponds to the assembly architecture, the following become easier:

  • Parts preparation

  • Material issuing

  • Cost management by module

  • Work instructions

  • Change management

  • Missing-part inspection

31. Assembly Sequence and Material Supply

Parts should be supplied according to the assembly sequence.

Material-Supply Methods

  • Kitting

  • Module-based sets

  • Sequence-based supply

  • Kanban

  • Barcode-based issue

Supplying parts at the wrong time may cause:

  • Workspace congestion

  • Part mixing

  • Damage

  • Missing parts

  • Application to the wrong model

32. Outsourced Assembly Architecture

When modules are assembled by an external supplier, interface conditions and inspection responsibilities should be clearly defined.

Items to Include in Outsourced Assembly Specifications

  • Assembly drawings

  • Parts list

  • Datum surfaces

  • Tightening torque

  • Assembly sequence

  • Inspection criteria

  • Test method

  • Packaging method

  • Shipping condition

  • Traceability records

The function and interface of outsourced modules should be verifiable during incoming inspection.

33. Assembly Architecture for Field Installation

Large machines may be separated into multiple modules for transportation.

Field-Separation Boundaries

  • Frame joints

  • Locating pins

  • Electrical connectors

  • Pneumatic connectors

  • Network connections

  • Safety interfaces

Field-Reassembly Sequence

  1. Position the base.

  2. Perform leveling.

  3. Locate the modules.

  4. Fasten the modules.

  5. Connect the cables.

  6. Connect the piping.

  7. Connect grounding.

  8. Verify alignment.

  9. Verify I/O.

  10. Perform recommissioning.

34. Transportation Disassembly and Reassembly Repeatability

Connections that are disassembled for transportation should be designed differently from ordinary fastening points.

Required Elements

  • Locating pins

  • Precision pilots

  • Reference markings

  • Reusable connectors

  • Cable identification

  • Piping identification

  • Transportation fixtures

  • Reassembly measurement criteria

If position is determined only by bolts, accuracy may change after field reassembly.

35. Assembly Time and Process Balancing

In parallel assembly lines, balancing operation time is important.

Review Items

  • Standard time for each process

  • Bottleneck processes

  • Number of operators

  • Shared tools

  • Inspection time

  • Waiting time

  • Rework time

If assembly modules are divided too finely only to reduce individual operation time, logistics and interfaces may become unnecessarily complex.

36. Assembly Automation Potential

Where production volume is high, some assembly tasks may be automated.

Automation Targets

  • Screw fastening

  • Press-fitting

  • Adhesive application

  • Label application

  • Leak testing

  • Electrical testing

  • Vision inspection

To apply automated assembly, the following should be considered:

  • Part-supply orientation

  • Locating geometry

  • Tolerances

  • Fastening detection

  • Reject handling

  • Traceability

37. Assembly Change Management

A design change may affect the assembly sequence.

Examples:

  • Change in part geometry

  • Change in fastening direction

  • Change in sensor position

  • Change in cable route

  • Addition of a module

  • Change in cover structure

The following should be reviewed after a change:

  • Precedence relationships

  • Tool accessibility

  • Inspection timing

  • BOM

  • Work instructions

  • Jigs

  • Operation time

  • Existing inventory

38. Standardization of Assembly Work

The assembly sequence should be managed through standard documents rather than operator experience.

Contents of Standard Work Instructions

  • Process number

  • Operation name

  • Parts to prepare

  • Tools to use

  • Assembly references

  • Work sequence

  • Fastening conditions

  • Inspection method

  • Precautions

  • Completion criteria

Important operations should include photographs, sectional views, enlarged details, and orientation markings.

39. Digital Assembly Review

Assembly feasibility can be reviewed in advance using 3D CAD or digital models.

Review Targets

  • Part insertion path

  • Tool access

  • Operator access

  • Lifting route

  • Interference

  • Disassembly path

  • Cable routes

  • Assembly sequence

Digital review should reflect actual workspace and tool dimensions.

40. Assembly Sequence Simulation

For complex machines, the assembly sequence can be simulated.

Purposes

  • Verify precedence relationships

  • Review parallel operations

  • Predict working time

  • Check collisions

  • Review operator safety

  • Review tools and jigs

  • Review installation space

Simulation is effective for reducing sequence-related errors before assembly begins.

41. Assembly Traceability

Critical assembly operations may require recorded history.

Record Items

  • Machine serial number

  • Assembly-module number

  • Operator

  • Working time

  • Tightening torque

  • Measurement results

  • Adjustment values

  • Inspection results

  • Parts used

  • Rework status

Module numbers in the assembly architecture should be linked to actual traceability numbers.

42. Major Design Deliverables

Deliverable

Purpose

Assembly Architecture Diagram

Defines the complete assembly hierarchy and module relationships

Assembly Breakdown Structure

Decomposes the machine into assembly units

Module Interface Specification

Defines connection conditions between modules

Datum Hierarchy

Defines the hierarchy and transfer relationships of assembly datums

Assembly Precedence Diagram

Defines precedence relationships among operations

Assembly Sequence Chart

Defines the complete assembly sequence

Parallel Assembly Plan

Defines modules that can be assembled in parallel

Intermediate Inspection Plan

Defines locations and timing of intermediate inspections

Hold Point List

Defines mandatory inspections before proceeding

Tool and Access Review

Reviews tool and operator accessibility

Module Test Plan

Defines functional testing for each module

Field Installation Sequence

Defines the field-reassembly sequence

Assembly Work Instruction

Defines the standard method for each operation

Assembly Traceability Record

Records assembly history and measurement results

43. Assembly Architecture Review Questions

Module Structure

  • Is the machine divided into functionally appropriate modules?

  • Are module size and weight manageable?

  • Can each module be tested independently?

  • Is outsourced or parallel assembly possible?

Interfaces

  • Are mechanical, electrical, and pneumatic interfaces clearly defined?

  • Are module positioning and fastening functions separated?

  • Can the modules be repeatedly disassembled and reassembled?

  • Are interface-inspection methods defined?

Datum System

  • Are the reference module and reference component clear?

  • Are upper-level and lower-level datums connected?

  • Can datum surfaces be measured during assembly?

  • Can the same datums be used during field reassembly?

Assembly Sequence

  • Are precedence relationships clear?

  • Are internal parts installed before covers?

  • Is the installation timing of precision parts appropriate?

  • Are temporary fastening and final fastening distinguished?

Inspection

  • Are intermediate inspection points defined?

  • Have items that cannot be inspected after final assembly been identified?

  • Are required Hold Points defined?

  • Are module tests and complete-machine tests distinguished?

Workability

  • Are tools and measuring instruments accessible?

  • Is a lifting route available for heavy parts?

  • Is operator posture appropriate?

  • Does rework avoid excessive disassembly?

Product Variants

  • Are assembly changes defined for each option?

  • Does the BOM correspond to the assembly structure?

  • Can options be identified early in assembly?

  • Can common modules be reused across different models?

44. Assembly Sequence Review Questions

  • Are the assembly start and completion points clearly defined?

  • Are the inputs and outputs of each process defined?

  • Are parallel and serial operations distinguished?

  • Are precision parts installed after datum establishment?

  • Is temporary fastening applied before adjustment?

  • Is remeasurement performed after final fastening?

  • Are wiring and piping routes kept open?

  • Is internal inspection completed before cover installation?

  • Does the sequence prevent part damage and contamination?

  • Have rework and component replacement been considered?

  • Is the field-installation and reassembly sequence defined?

  • Are work standards and inspection criteria updated together after changes?

45. Conclusion

Assembly Architecture and Sequence defines how a machine is divided into assembly units and how those units are combined according to specific references and sequences.

Its core purpose is not merely to list assembly operations.

The following relationships must be designed systematically:

  • Product functions and assembly modules

  • Higher-level modules and subassemblies

  • Datum surfaces and datum transfer

  • Part installation and preceding operations

  • Temporary fastening and final fastening

  • Assembly operations and intermediate inspection

  • Module testing and complete-machine integration testing

  • Tool accessibility and operator safety

  • Product options and assembly variations

  • Factory assembly and field reassembly

An appropriate assembly architecture organizes the machine into manageable modules and allows each module to be assembled, inspected, and replaced independently.

An appropriate assembly sequence establishes datums first, protects precision parts, maintains conditions for inspection and adjustment, and reduces unnecessary disassembly and rework.

Through this approach, assembly becomes not an operator-dependent activity, but a standardized production system capable of repeatedly reproducing the same functionality and accuracy.